Latest Carmel road construction updates

Main Street & Lexington Boulevard roundabout

There will be disruptions and intermittent closures through Saturday, July 8 for milling, final concrete work and final paving. Contractors will finish sod, striping and other final items with a substantial completion by the end of the following week, weather permitting.

111th Street & Spring Mill Road roundabout

111th Street between Illinois Street and Spring Mill Road will be closed for three weeks for the construction of a roundabout at the entrance to the Bridges development and the Spring Mill Place neighborhood. This roundabout is being constructed by a developer and not the City of Carmel.

3rd Avenue SW

Construction is underway on 3rd Avenue SW between Autumn Drive and 2nd Street SW. The road will be closed for approximately 18 months. Access to businesses along 3rd Avenue will be maintained for the duration of the project.