Beginning on or after Monday, May 20, the contractor will begin placing the next lifts of asphalt along Allisonville Road south of 146th Street. This work is anticipated to take four days to complete.
The contractors will use traffic phases to complete this work. Please reduce speeds and follow instructions of the flaggers for your safety and the safety of the construction crews. All work items and dates are subject to weather as both asphalt and concrete can be adversely affected if placed in the rain.
Use extreme caution while driving through this construction zone.
Click here for more project information.