Fishers road construction updates, week of March 6

State Road 37

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

State Road 37 & 141st Street

A pre-construction phase at SR 37 and 141st Street is currently in place. During this phase, 141st Street will be transitioned to a Right-In-Right-Out (RIRO) traffic configuration.

This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate all backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street.

The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Fall of 2023. View detour routes here.

131st Street

Comcast is currently doing utility work on 131st Street from Howe Road to Promise Road then north on Promise Road to 141st Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

106th Street & Hoosier Road

Utility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here.

106th Street & Cumberland Road

During the week of March 6, Duke Energy will do tree trimming on 106th Street between Cumberland Road and Fall Road. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Allisonville Road

During the week of March 6, DPW will perform median landscaping on Allisonville Road between Eller Road and 106th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Cumberland Road

During the week of March 6, Duke Energy will do tree trimming on Cumberland Road between 106th Street and 116th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Florida Road

From Tuesday, March 7 through Friday, March 10, Florida Road between Southeastern Parkway and 113th Street will be closed each day between 9 a.m. and 2 p.m. to allow contractors to make utility crossings. Steel plates will be placed at the end of each day to allow for travel outside of those times.

Geist Road

During the week of March 6, Duke Energy will do tree trimming on Geist Road between Fall Creek Road and 106th Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Geist Greenway

Pile driving activities are currently taking place near Thorpe Creek as part of the Geist Greenway Project through Monday, March 20. For general project information, please visit playfishers.com/299/Geist-Greenway.

Fall Creek Road

Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.

Capital Project & Development Dashboards

A Capital Project Dashboard is now available on Drive Fishers. The dashboard was created to offer an interactive mapping and data tool, which allow users the ability to filter data and find the most current details on Engineering Capital Projects. View the Capital Project Dashboard here.

The Planning & Zoning Department has a new Development Dashboard where you can view all development projects that are under construction or in the process of being reviewed. This is viewable on the Planning & Zoning Homepage here.