State Road 37 & 141st Street
Preliminary construction work is underway at SR 37 and 141st Street. During this time pavement markings and concrete barriers will be placed. There will be no closures during this phase, only intermittent lane restrictions during the hours of 9 a.m. to 3 p.m.
Find construction updates at 37thrives.com.
141st Street & Promise Road roundabout
The City of Noblesville plans to begin construction on a roundabout at 141st Street and Promise Road on or after Monday, June 17. Once construction begins this closure will last approximately 60 days. The detour route signage will be in place prior to the closure. For your safety, please do not enter the construction zone. There could be open trenches or other obstacles that are unsafe.
Click here for more project information.
106th Street & Cumberland Road
Starting Monday, June 17, there will be lane restrictions at 106th Street and Cumberland Road while Verizon contractors install underground equipment. Lane restrictions will be in place between the hours of 9 a.m. and 3 p.m.
Fishers Trade Center
The contractor will work north of 135th Street and south of 141st Street the week of June 17. The construction traffic route is one-way heading north from 135th to 141st.
Click here to see a map.
Road resurfacing projects
The contractor is continuing work in Sunblest neighborhood. The week of June 17, road resurface work will take place on 126th Street between Olio Road and Thorpe Creek Parkway. Traffic will be down to one lane with flaggers on site to direct traffic from 7:30 a.m. to 5:30 p.m. on Monday, June 17 and from 7:30 a.m. to 5:30 p.m. on Tuesday, June 18.
Additionally, the contractor will begin work mid-week the week of June 17 and has placed door hangers in the Fox Run Neighborhood.
Towards the end of the week of June 17, the contractor will move into the Hillsborough neighborhood.
Residents should refrain from parking their vehicles on the street during active construction operations.
Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.
For additional project information, view the Capital Project Dashboard here.
View the Road Resurface Overview Map here.
Roadways and neighborhoods are prioritized based on the PASER rating condition of their pavement. You can see a map here.