Fishers road construction updates, week of May 29

State Road 37 & 141st Street

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

I-465 & I-69

The ramp from Interstate 69 North to 82nd Street and the ramp from 82nd Street to I-69 North is currently closed through late 2023. For detour routes and additional project information, visit ClearPath465.com.

Nickel Plate Trail

The City of Fishers is working on the completion of the Fishers portion of the Nickel Plate Trail. The remaining paving work from 96th Street to 106th Street is underway, and construction crews are currently working to clear and prep the area for paving. In the coming weeks, construction crews will begin the paving process.

Beginning on or after Monday, June 5, Hague Road will be closed at the NPT crossing for construction of the speed table and is anticipated to reopen by Monday, June 12. The detour shall use Crosspoint Blvd. to 106th Street. Click here to see the detour route.

To learn more about the Nickel Plate Trail, view the Capital Project Dashboard here.

116th Street

Beginning on Wednesday, May 31, daily lane restrictions will be in place on 116th Street between Commercial Drive and Inspiration Drive as well as Exit Five and Ikea Way for storm sewer BMP work through Monday, June 5.

Cumberland Road

There are daily lane closures currently on Cumberland Road just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed.

126th Street

Beginning on or after Tuesday, May 30, 126th Street between Royalty Drive and Bellingham Boulevard will be closed for median and crosswalk construction and is anticipated to reopen by Friday, June 30. The detour shall use Olio Road to Southeastern Parkway. Click here to see the detour route.

146th Street & Allisonville Road

Phase 1 of construction for the grade separation intersection improvement is taking place at 146th Street and Allisonville Road. One thru lane and one left-turn lane in all directions will be closed through the intersection.

Beginning on or after Tuesday, May 30, Lynn Avenue (south of 146th Street, east of Allisonville Road) will be closed to all thru traffic for utility relocation work. These daytime closures will last through Friday, June 2, from the hours of 9 a.m. to 4 p.m. In addition to these closures, the worksite speed limit will be 35 mph. Please exercise caution while driving through this construction zone.

For additional project information, click here.

106th Street

Utility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here.

106th Street & Kinkaid Drive

Beginning on or after Monday, June 5, Phase 1 will begin for construction of a new concrete median on 106th Street and to modify Kincaid Drive to a right-in/right-out entrance. During this phase, access to Kincaid Dr. from 106th Street will be restricted. The detour shall use Lantern Road to Sunlight Drive. Phase 1 is anticipated to be completed by Friday, July 7. Click here to see the detour route.

Phase 2 is anticipated to begin on Monday, July 10. During this Phase, lane restrictions will be in place on 106th Street and both the roundabout at 106th Street and I-69 and 106th Street and Lantern Road will be converted into a single lane for the duration of this Phase. This Phase is anticipated to be completed by Friday, July 28.

Fall Creek Road

Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.

Geist Greenway

Stone is currently being placed between 126th Street and Valley Crossing Drive as part of the Geist Greenway Project. When material is brought in, there will be an increase in construction traffic. Traffic will be briefly stopped as trucks are entering and exiting the road. For general project information, please visit playfishers.com/299/Geist-Greenway.

Tree Trimming

During the week of May 29, Duke Energy will be tree trimming at the following locations. Lane restrictions will be in place between 9 a.m. and 3 p.m.

  • Allisonville Road, near Eller Road
  • Brooks School Road between 116th Street and Fall Creek Road
  • Eller Road between 106th and 116th streets

Resurfacing Projects

Curb and ramp reconstruction is complete in Wildwood Estates and Rolling Knoll as part of the 2023 Resurfacing Project. Prior to road resurfacing, expected to begin on or after June 5, residents will be notified via street signage for street parking restrictions.

ADA ramp and curb reconstruction is currently taking place on Sunblest Boulevard between Allisonville Road and Orchard Boulevard as part of the 2023 Resurfacing Project. Homeowners will be notified via door hangers prior to any curb restoration near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.

For additional project information, view the Capital Project Dashboard here.