New Binford Boulevard ramp to open next weekend

Graphic provided by INDOT

The new ramp from southbound Interstate 69 to southbound Binford Boulevard is expected to open on or after Sunday, May 3, marking another milestone on the Clear Path 465 Project.

Overnight ramp and lane restrictions are scheduled next week in northeast Indianapolis as crews prepare to shift traffic and open the new ramp.

Drivers can expect the following nightly closures from 9 p.m. to 6 a.m.:

  • Monday, April 27: Ramp from northbound Binford to northbound I-69 closed
  • Monday, April 27 through Thursday, April 30: One lane closed on northbound Binford and northbound I-69 between the I-465/I-69 interchange and 96th Street
  • Tuesday, April 28 through Thursday, April 30: Ramp from southbound I-69 to southbound Binford closed

Ramp closures expected next weekend

Ramp closures are scheduled next weekend to complete the traffic switch and open the new ramp from southbound I-69 to southbound Binford Boulevard. The following ramps are expected to close at 9 p.m. on Friday, May 1 and reopen by 6 a.m. on Sunday, May 3 unless otherwise noted:

  • Ramp from southbound I-69 to southbound Binford Boulevard closed
  • Ramp from 96th Street to southbound I-69 closed
  • Ramp from 82nd Street to southbound I-465 closed
  • Ramp from southbound I-69 to southbound I-465 closed (overnight Friday only)
  • Ramp from southbound I-69 to westbound I-465 closed (Saturday 6 a.m. to Sunday 6 a.m.)

Lane restrictions will also be in place. Crews will be striping pavement, moving barrier wall, and adjusting overhead signage to shift traffic on I-69.

Emergency access will be maintained during the work. Actual dates and anticipated work may be adjusted if inclement weather or other unforeseen circumstances occur.