Towne Road
All weather and progress permitting
- Main Street is now open
- 126th Street is now closed; scheduled to open the week of Aug. 18
- Glebe Street is now closed; scheduled to open the week of Sept. 1
- 116th Street is closed but will open to traffic by end of day Aug. 5
- Final restoration of the lawns at 106th, 116th, and Main streets is in progress
- Towne Road over I-465 is closed for bridge work by INDOT. Updates will be provided as they are received from INDOT.
College Avenue construction
Phase II of the North College Avenue reconstruction project (I-465 to 106th Street) will begin on or after Monday, Aug. 4 and continue through the end of the year. This phase includes full reconstruction of the northbound lanes and work on the east side of the road, including most of the new roundabout at Pennsylvania Parkway.
A 30-day closure around October or November will be in place to complete the west side of the roundabout. Northbound traffic will reopen before winter which will allow two-way traffic during the schools’ winter break.
Affected driveway aprons in this phase of construction will be temporarily removed and replaced with stone to maintain access during construction.
If you have questions, refrain from approaching the contractors, but please do reach out to Engineering Administrator Joshua Kirsh at jkirsh@carmel.in.gov.
Street Department paving
Due to the rainy weather from July 25 and July 28, paving work was delayed. New paving dates are scheduled below, weather permitting:
- Cool Creek Estates – In progress; will be completed on Saturday, Aug. 2.
- Red Oak Lane – In progress, will be completed by Monday, Aug. 4.
- West 116th Street between Shelborne Road and Towne Road – Paving underway Monday, Aug. 4.