State Road 37 & 141st Street
The final interchange of the State Road 37 Improvement Project will officially begin construction at 141st Street and SR 37 this summer.
The pre-construction meeting for the project team will take place at the end of May with the schedule to soon follow.
One important note: to ease the construction burden in the area, the work will not begin until Hamilton County’s 146th Street closure at Allisonville Road re-opens. The full timeline for the 141st Street interchange will be provided after project bids are accepted.
What to expect this summer
The interim traffic configuration that has been in place will be adjusted to accommodate temporary pavement construction leading up to the next phase, which will be construction on the west side of 141st Street. During this time, all traffic will be moved to the east side, with northbound and southbound lanes open at all times on SR 37 (intermittent restrictions will be communicated).
All construction updates will be posted to DriveFishers on X and 37 Thrives on Facebook. Please visit 37Thrives.com to sign-up for email updates.
To navigate the merge, remember:
- Use the accel lane to gain speed, not stop.
- Use your mirrors and pay attention.
- Look for a gap in SR 37 traffic and safely merge.
To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.
Road resurface projects
ADA ramp and curb reconstruction will begin in Lantern Ridge starting the week of May 13.
Towards the end of the week, the contractor will continue into Sunblest as part of the 2024 Resurfacing Project. Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.
For additional project information, view the Capital Project Dashboard here.
View the Road Resurface Overview Map here.
Roadways and neighborhoods are prioritized based on the PASER rating condition of their pavement. You can see a map here.
Florida Road
During the week of May 13, there will a road closure in place on Florida Road north of 113th Street to allow for resurfacing that will be completed in two phases, which includes a full depth dig out and rock, base, and binder installation.
Phase 1 will take place on May 13 and 14, and Phase 2 will be May 15 and 16. On May 17, both sections will be resurfaced with traffic restrictions in place, and flaggers will be on site directing traffic. View a map of the closure here.
Barrett Law East & West
- Parkside/Publishers: Work on Barrett East is substantially complete.
- Fishers Trade Center: The contractor will work on road reconstruction north of 135th Street and south of 141st Street the week of May 13. The construction traffic route is one way, heading north from 135th to 141st.