Fishers road construction updates, week of Aug. 9

State Road 37 & 146th Street

All left-turn lanes are currently restricted on SR 37 and on 146th Street with traffic moved to the interior lanes. Thru traffic and right turns on SR 37 and 146th Street will remain open. Drivers are encouraged to seek alternate routes for all left-turn access. View an alternate route map here.

State Road 37 & 131st/135th Streets

The west side of 131st Street at SR 37 is currently closed as work progresses on the interchange. SR 37 will remain open both north and southbound. SR 37 southbound left and right turns onto 131st Street will be restricted. Westbound turns onto SR 37 will also be restricted on 131st Street. Click here to view the detour map.

The northbound SR 37 right turn lane onto 135th Street is currently closed from 131st Street to approximately halfway to 135th Street for Phase 1 construction. This portion of the dedicated turn lane will not reopen to regular capacity until the interchange is complete.

Please drive with caution through these areas. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

116th Street at the Nickel Plate Trail

116th Street in downtown Fishers has fully opened to four lanes of traffic after the completion of the Nickel Plate Trail tunnel. Upon completion of the Nickel Plate Trail, slated for spring 2022, pedestrians will access the trail via the tunnel to provide safe passage beneath 116th Street.

Construction in the area related to the downtown development projects will impact the roadway at various times in August and September. Beginning the week of Aug. 9, 116th Street will be reduced to one lane in each direction between Municipal Drive and Maple Street between 9 a.m. and 3 p.m. for final asphalt surface placement at the Nickel Plate Trail. All lanes are anticipated to reopen by Thursday, Aug. 12.

Also beginning the week of Aug. 9, gas main work will be taking place between 9 a.m. and 3 p.m. at the intersection of 116th Street and Fishers Center Drive and is anticipated to last three to five days. Click here to view restrictions and the detour map.

Britton Ridge

ADA ramp work is currently taking place in Britton Ridge and is anticipated to be completed in August.