Starting today, closures begin at Towne Road roundabouts
Submitted by City of Carmel
The City of Carmel is moving forward with several infrastructure projects this summer and fall with the goal of improving pedestrian safety, expanding trail access, and enhancing neighborhood connectivity. Residents and commuters should expect road closures, lane restrictions, and detours in various parts of the city.

Pease
“This work goes beyond just sidewalks and crosswalks – it’s about improving how people move around Carmel,” City Engineer Bradley Pease said. “While construction can be inconvenient in the short term, these projects will make our streets safer and more accessible for years to come.”
Towne Road closures
Starting today, June 25, construction will begin on raised pedestrian crosswalks at seven roundabouts along Towne Road. Each roundabout will close for approximately one month, with detours posted and closures staggered as follows:
- Phase 1: 106th Street & Towne Road, 131st Street & Towne Road
- Phase 2: 116th Street & Towne Road, 136th Street & Towne Road
- Phase 3: 126th Street & Towne Road, Glebe Street & Towne Road
- Final Phase: 141st Street & Towne Road
The full project is expected to be completed by October 2025. Be sure to drive carefully and follow all detour signage.
Multi-use path projects & road impacts
Several multi-use path projects are also underway or preparing to begin across the city. These improvements will fill sidewalk and trail gaps, improve pedestrian safety, and expand access to neighborhoods, parks and schools.
Current construction
- 116th Street (Shelborne Road to Towne Road): flagging through late July; completion expected July 2025
- Clay Center Road (Clay Spring Drive to Clay Corner): 90-day full closure begins mid-July; completion October 2025
- 96th Street (Ditch Road to Spring Mill Road): three-day full closure expected in August; completion October 2025
Beginning soon
- 99th Street (Westfield Boulevard to Haverstick Road): westbound closure for 30 days as of June 23
- 141st Street (Little Eagle Creek to Ditch Road): westbound closures start in July; completion by November 2025
Future projects in design
- 136th Street (Towne Road to Ditch Road, Ditch Road south of 136th Street): begins fall 2025, complete spring 2026
- Westfield Boulevard (99th Street to 116th Street): Phase 1 begins August 2025, complete fall 2025; Phase 2 (includes new bridge) will complete in spring 2026
- 111th Street (Westfield Boulevard to Monon Greenway): includes a 14-day full closure near the Monon in spring 2026; complete summer 2026
Stay informed
Your patience is appreciated as these improvements take shape. For additional support, please contact Engineering Administrator Joshua A. Kirsh at jkirsh@carmel.in.gov or (317) 571-2441.