Carmel road construction updates

Monon Greenway at Carter Green

The Monon Greenway trail in the City Center area is still closed for construction. This section was temporarily opened during CarmelFest for event traffic. However, due to ongoing construction and improvements underway, pedestrians and cyclists must stay out of the area for safety purposes.

Main Street at 1st Avenue NW

On Monday, July 18, expect a closure of Main Street (east/west travel) for one day while the stamped asphalt crosswalks are completed on Main Street. On Tuesday July 19, expect Veterans Way and 1st Avenue NW to close for one day while the stamped asphalt crosswalks are completed (north/south travel).

1st Avenue NW Duke Transmission

This project will be substantially completed on or around July 25. Sidewalk completion will take place soon after. Due to supply chain issues and utility conflicts, the work in this area has been delayed from the originally scheduled completion date of mid-July.

Main Street roundabouts

Main Street continues its closure at Richland Avenue and Lexington Boulevard for construction of two roundabouts. Access to Carmel Christian Church and the educational buildings on the south side of Main Street will be maintained from the east side of the project along Main Street with the majority of construction completed prior to the start of school in August.

Keystone bridge overlays

There will be full closures of the following bridges over Keystone Parkway. All closures are planned to begin Friday night, work through Sunday and open late Sunday or early Monday morning.

  • Carmel Drive: Scheduled for weekend of July 16
  • Smoky Row: Scheduled for weekend of July 23
  • Main Street: Scheduled for weekend of Sept. 10
  • 116th Street: Scheduled for weekend of Sept. 17

There will be some concrete pavement patches on the southbound ramp from 116th Street to Keystone Parkway from Sept. 19 to 25. No closures are anticipated; the ramp will only be down to a single lane.

Keystone Parkway

Crews are in the process of sealing cracks on Keystone resulting in some lane restrictions for the remainder of July (weather dependent).