Fishers road construction updates, week of March 20

State Road 37

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

State Road 37 & 141st Street

A pre-construction phase at SR 37 and 141st Street is currently in place. During this phase, 141st Street will be transitioned to a Right-In-Right-Out (RIRO) traffic configuration.

This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate all backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street.

The full timeline for the 141st Street interchange will be provided after project bids are accepted in the summer of 2023. View detour routes here.

Cumberland Road

There are daily lane closures currently on Cumberland Road, just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed and is estimated to reopen by Friday, March 24.

131st Street

Comcast is currently doing utility work on 131st Street from Howe Road to Promise Road then north on Promise Road to 141st Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

106th Street & Hoosier Road

Utility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here.

106th Street & Cumberland Road

During the week of March 20, Duke Energy will be tree trimming on 106th Street, east of Cumberland Road. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Cumberland Road

There will be daily lane restrictions between 9 a.m. and 3:30 p.m. on Cumberland Road between 106th and 116th streets through Friday, March 24 for tree clearing as part of the Cumberland Road Reconstruction project. There may be times when a short-term full road closure will be needed. Finding an alternate route is recommended during this time. For additional project information, view the Capital Project Dashboard here.

Fall Creek Road

Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.

Florida Road

Beginning on or after Monday, March 20, Florida Road between 104th and 113th streets will be under lane restrictions for tree clearing work between 8 a.m. and 4 p.m. The estimated project completion date is Friday, March 24.

Geist Greenway

Pile driving activities are currently taking place near Thorpe Creek as part of the Geist Greenway Project through Monday, March 20. When material is brought in for fill sections, there will be an increase in construction traffic on Valley Crossing Drive. Traffic will be briefly stopped as trucks are entering and exiting the road. For general project information, please visit playfishers.com/299/Geist-Greenway.

Geist Road

During the week of March 20, Duke Energy will be tree trimming on Geist Road, north of Fall Creek Road. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Mollenkopf Road

During the week of March 20, Duke Energy will be tree trimming on Mollenkopf Road, between 96th and 106th streets. Lane restrictions will be in place between 9 a.m. and 3 p.m.

Resurfacing Projects

ADA ramp and curb reconstruction is currently taking place in Winding Creek as part of the 2023 Resurfacing Project. Homeowners will be notified via door hangers prior to any curb restoration near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. For additional project information, view the Capital Project Dashboard here.

Development Dashboards