Latest Carmel road construction updates

Graphic provided by City of Carmel

Towne Road
All weather and progress permitting

The roundabouts at 106th, 116th, and Main streets are open to traffic.

  • 126th Street is expected to open on or after Aug. 20.
  • 136th Street closes on or after Aug. 21.
  • Glebe Street is expected to open on or after Aug. 25.
  • Towne Road Bridge over I-465 is an INDOT project that has an expected completion of early 2026.

College Avenue construction

North College Avenue will be opening southbound from 106th Street to 96th Street, the week of Aug. 18 while contractors will conduct work in the northbound lane of College Avenue.

146th Street & Hazel Dell

Beginning on or after Monday, Aug. 18, between the hours of 9 a.m. and 3 p.m., drivers should expect lane restrictions for subsurface utility locates. One lane each direction will remain open at a minimum. The estimated completion date is Friday, Aug. 22.

126th Street bridge rehabilitation

126th Street between Brookshire Parkway and Royce Court is closed for bridge rehabilitation with an expected completion date of mid-late October.

Local traffic will continue to have access to their homes, while thru traffic is asked to use the posted detour of Keystone Parkway – 131st Street – Gray Road.