State Road 37 & 141st Street
Please note the continued lane restrictions on SR 37 North and South, approaching the 141st Street Interchange.
As of July 23, the west side of 141st Street at SR 37 has closed for the next phase of construction. Traffic will transition to the east side, with SR 37 north and southbound lanes remaining open. This closure will remain in place throughout 2024.
Please review detour routes to plan ahead during this time (141st Street, SR 37 West, and SR 37 East). Thank you for your continued patience and remember to drive cautiously and safely through construction areas.
Find construction updates at 37thrives.com.
Lane restrictions on 116th Street
On Wednesday, Aug. 14 there will be lane restrictions in place from 9 a.m. to 3 p.m. on 116th Street between Municipal Drive and Lantern Road. Crews will be demolishing the old Plumbers Supply Building.
South Street
There will be a two-phase road closure on South Street for utility installation between Lantern Road and the Nickel Plate Trail.
- Phase 1: Aug. 5 to 19 (weather dependent)
- Phase 2: Aug. 19 to 26 (weather dependent)
First Internet Bank Building Parking Garage
- Access will remain open at all times.
Hotel Nickel Plate Access
- South Street drive access will be restricted.
- Use 116th Street for access.
- Visitors may also park on the west side of the hotel, accessible off 116th Street, after the trail.
Please proceed through the area with caution. We appreciate your understanding and cooperation during this essential work.
Click here to see a map of the closure.
141st & Prairie Lakes roundabout
Construction crews have begun preliminary work for the construction of a new roundabout at the intersection of 141st Street and Prairie Lakes Boulevard/Old Oak Lane.
Beginning on or after Aug. 19, the intersection will be closed to thru traffic. Access to Woods of Britton apartments will be maintained off Cumberland Road only during this first phase. The 141st Street access to Prairie Lakes will be closed and access will be off Cumberland Road and 146th Street. View the map here.
126th Street & Southeastern Parkway roundabout
This roundabout is now open but remains an active construction site with intermittent lane restrictions. The new roundabout will also include a connection for the development of Hunters Run. The project will rehabilitate or reconstruct the pavement, add curb and gutter with storm sewers, and multi-use paths and/or bicycle lanes.
Sidewalk Improvement Project
Restoration will be ongoing in the Ridgefield and Sweet Briar North Neighborhoods the week of Aug. 12. The sidewalk work will consist of removal and replacement of sidewalk panels which pose a toe kick trip hazard. Sidewalk within driveways is not included in the scope of this project.