As Noblesville continues to address the most necessary infrastructure needs within the city, the next series of street rehabilitation project begins today. The upcoming schedule – weather permitting – includes:
- Thursday, Aug. 9 – Begin milling and paving in North Harbour – Essex Court; Devonshire Court; Surrey Hill; Sedwick Court; Shannon Court; Whitley Court; and Westchester Drive (North Harbour Drive to Cheshire Circle).
- Friday, Aug. 10 – Begin milling and paving in Meadows – Golden Meadow Way (191st Street to Amber Way); Trillium Court; Hyacinth Court; Cornelian Court; Mayapple Court; Harbinger Court; Timothy Lane; Bur Oak Court; Firelight Court; Corn Poppy; Chicory Court; Magenta Drive (Meadows Boulevard to Amber Way); Grasshopper Court; Sandpiper Court; Kestral Court; Blue Flax Court; and Sparrow Court.
- Monday, Aug. 13 – Begin milling and paving in Stony Creek Village – Lowell Drive and Aulton Drive.
- Thursday, Aug. 16 – Begin milling and paving 1.6 miles of alleys in Old Town Noblesville. Alleys being worked on will be closed for the day during this portion of the project and reopened each evening.
Signs will be placed onsite a week before construction begins and mailings will be sent to affected homeowners. This construction will cause minor inconveniences, including traffic delays, temporary loss of street parking, construction noise and access restrictions. All measures will be taken to facilitate construction in a quick and timely fashion.
Noblesville budgeted $2.6 million to address road and alley repaving and repair work to sidewalks and ramps as part of the 2018 Street Rehabilitation Project. For more information, contact the Engineering Department at 317-776-6330.