Fishers road construction updates, week of Nov. 1

State Road 37 & 146th Street

All left-turn lanes are currently restricted on SR 37 and on 146th Street with traffic moved to the interior lanes. Thru traffic and right turns on SR 37 and 146th Street will remain open. Drivers are encouraged to seek alternate routes for all left-turn access. View an alternate route map here.

State Road 37 & 131st Street

131st Street at SR 37 is currently closed as work progresses on the interchange. SR 37 will remain open both north and southbound. Click here to view the detour map.

The anticipated completion of the 131st Street work that will allow right in/right out movements for southbound SR 37 and 131st Street is scheduled for Wednesday, Nov. 10 or after.

Please drive with caution through these areas. To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

116th Street at the Nickel Plate Trail

116th Street in downtown Fishers has fully opened to four lanes of traffic after the completion of the Nickel Plate Trail tunnel. Upon completion of the Nickel Plate Trail, slated for Spring 2022, pedestrians will access the trail via the tunnel to provide safe passage beneath 116th Street.

Nickel Plate Trail

Paving of the northern portion of the Nickel Plate Trail is currently taking place, beginning at 131st Street and moving north of 146th Street over the coming weeks. The project is anticipated to take approximately six weeks to complete, pending weather delays. A speed table (roadway crossing) and pedestrian warning signal for motorists will be installed at 141st Street during this construction. Until paving is complete, this northern portion of the railbed remains closed and no trespassing is permitted. The northern portion is anticipated to be open for pedestrian use by the end of October.

Hamilton County Highway Project

Lane closures are in effect for 116th Street between River Road and Eller Road for the rehabilitation the 116th Street bridge over the West Fork of the White River. One lane of traffic in each direction will be maintained at all times on 116th Street throughout construction. Lane closures are expected to be lifted by Tuesday, Nov. 9.

In addition, River Drive West is closed at 116th Street for the first project phase. Residents should use the signaled intersection at 116th Street and River Drive East for the duration of the closure.