Fishers road construction updates, week of Feb. 6

State Road 37

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

State Road 37 & 141st Street

Due to an equipment malfunction with the pavement marking removal, temperatures and weather conditions, the traffic signal will remain in place for safety measures until the lane lines have been installed.

A pre-construction phase at SR 37 and 141st Street is currently in place. During this phase, 141st Street will be transitioned to a Right-In-Right-Out (RIRO) traffic configuration. This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate all backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street.

The full timeline for the 141st Street interchange will be provided after project bids are accepted in the Fall of 2023. View detour routes here.

106th Street & Hoosier Road

Beginning on Monday, Feb. 6, utility relocation will begin taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here.

Fall Creek Road

Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.

Snow & ice control

The Fishers Department of Public Works is responsible for providing snow and ice control for all dedicated streets within city limits. For additional information on the Snow and Ice Control Plan, snow maps, and to report snow concerns, visit the DPW Snow and Ice Control homepage here.