146th Street & Allisonville Road

Phase 2A traffic restrictions are currently in effect. These restrictions eliminate left turns from 146th Street onto Allisonville Road and reopen to two thru lanes on eastbound and westbound 146th Street.

Use extreme caution while driving through this construction zone. Flaggers will be present when lane or shoulder restrictions are necessary.

For additional project information, click here.

Fall Creek Road

From Monday, Aug. 7 through Friday, Aug. 11, there will be rolling closures on the Fall Creek Trail between 96th Street and Carroll Road for slurry sealing. Most of the closures will be between 7:30 a.m. to 6 p.m., but some sections will remain closed overnight while material cures.

Florida Road

Florida Road is currently closed to realign the S-curve and is anticipated to reopen by Monday, Aug. 21. Local traffic only between 113th Street and Southeastern Parkway. View detour route here.

96th Street & Allisonville Road

From Monday, Aug. 7 through Thursday, Aug. 10, overnight lane restrictions will be in place on Allisonville Road between 8:30 p.m. and 6 a.m. to allow for a water main installation for the residential development coming to the northwest corner of 96th Street and Allisonville Road.

106th Street & Allisonville Road

There is a sanitary sewer project currently taking place at Metro Airport at 106th Street and Allisonville Road. There are times where lane restrictions may be in place on Allisonville Road. Please use caution in this area.

106th Street & Hoosier Road

Prep work prior to the roundabout construction is currently taking place. Work will include tree clearing, utility relocation and storm sewer installation. For additional project information, view the Capital Project Dashboard here.

Cumberland Road

There are daily lane closures currently on Cumberland Road just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed.

Geist Greenway

Geist Greenway is now open between Valley Crossing to 126th Street. Work will resume on the trail south of Valley Crossing Drive on/or after Sept. 1 and remains closed until construction is finished. Construction continues to take place on Florida Road and between Bowline Drive and 104th Street. For general project information, please visit playfishers.com/299/Geist-Greenway.

Resurfacing Projects

ADA ramp and curb reconstruction is currently taking place in the Bristols as part of the 2023 Resurfacing Project. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.

On Monday, Aug. 7, work will begin to update and improve the ADA ramps at the Parks (Harvard, Oxford, and Princeton Park). On Monday, saw-cutting curb and sidewalk to prepare for the demolition of the existing ramps will take place. On Tuesday and Wednesday, there will be the removal of existing ramps and pouring concrete. This work will take place over the next three weeks in this neighborhood. After this work is completed, Rieth-Riley will then begin milling and paving operations.

For additional project information, view the Capital Project Dashboard here.

State Road 37 & 141st Street

To learn more about the State Road 37 Improvement Project and sign up to receive text updates, visit 37Thrives.com.

I-465 & I-69

The ramp from I-69 North to 82nd Street and the ramp from 82nd Street to I-69 North is currently closed through late 2023. For detour routes and additional project information, visit ClearPath465.com.

Nickel Plate Trail

The City of Fishers is working on the completion of the Fishers portion of the Nickel Plate Trail between Hague Road and 106th Street. The installation of pedestrian rail is currently taking place and pedestrian flashers are not operative at this time.