Fishers road construction updates, week of April 10

State Road 37 & 141st Street

A pre-construction phase at SR 37 and 141st Street is currently in place. During this phase, 141st Street will be transitioned to a Right-In-Right-Out (RIRO) traffic configuration.

This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate all backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street.

The full timeline for the 141st Street interchange will be provided after project bids are accepted in the summer of 2023. View detour routes here.

I-465 & I-69

Drivers will see an increase in construction along the Interstate 69 corridor in the coming months. This work will focus on reconfiguring the interchange at I-465 and I-69. New ramps will provide direct movements from eastbound I-465 and northbound I-465 to northbound I-69.

Binford Boulevard will also be reconstructed to separate local traffic from traffic entering and exiting I-69 and I-465. Access to I-69 from Binford Boulevard will remain open. Drivers can expect to see significant activity on I-69 at the 82nd Street interchange.

Nickel Plate Trail

The City of Fishers is working on the completion of the Fishers portion of the Nickel Plate Trail. The remaining paving work from 96th Street to 106th Street is underway, and construction crews are currently working to clear and prep the area for paving. In the coming weeks, construction crews will begin the paving process.

To learn more about the Nickel Plate Trail, view the Capital Project Dashboard here.

116th Street

On Sunday, April 9, there will be an overnight lane restriction between 9 p.m. and 4 a.m. on 116th Street between Commercial Drive and Fishers Pointe Boulevard for sanitary sewer cleaning.

On Tuesday, April 11, there will be an overnight lane restriction between 9 p.m. and 4 a.m. on westbound 116th Street between Cumberland Road and Exit 5 for storm inlet repair work.

131st Street

Comcast is currently doing utility work on 131st Street from Howe Road to Promise Road then north on Promise Road to 141st Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

126th Street

On Friday, April 14, lane restrictions will be in place on eastbound 126th Street between Spire View Drive and Champions Boulevard for storm inlet repair work.

Cumberland Road

There are daily lane closures currently on Cumberland Road just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed.

Southeastern Pkwy. & Cyntheanne Road

On Monday, April 10, lane restrictions will be in place at the Southeastern Parkway and Cyntheanne Road roundabout for storm sewer cleaning.

106th Street & Hoosier Road

Utility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here.

Fall Creek Road

Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.

Geist Greenway

Construction of the boardwalk is currently taking place as part of the Geist Greenway Project. When material is brought in for fill sections, there will be an increase in construction traffic on Valley Crossing Drive. Traffic will be briefly stopped as trucks are entering and exiting the road. For general project information, please visit playfishers.com/299/Geist-Greenway.

Masters Road

Beginning on Monday, April 10, Masters Road will be closed immediately east of Willowview Road as part of the Metro Airport Sanitary Sewer Project for approximately one week. Metro Airport can be accessed via Masters Road at 96th Street.

Resurfacing Projects

ADA ramp and curb reconstruction is currently taking place in Rolling Knoll and will then begin in Spyglass Hills as part of the 2023 Resurfacing Project. Homeowners will be notified via door hangers prior to any curb restoration near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions.

During the week of April 10, road resurfacing operations will begin taking place on Cyntheanne Road between 96th Street and Lin Road, Georgia Road between 96th and 104th streets, Willowview Road between Allisonville and Masters roads, Winding Creek Woods, Britton Park Road between 131st and 135th streets, and 131st Street between Allisonville Road and the Nickel Plate Trail. Rolling lane restrictions and flaggers will be in place.

For additional project information, view the Capital Project Dashboard here.