131st Street
Periodic lane restrictions will occur at the intersection of 131st Street and Cumberland Road as utility relocation work is completed.
Morgan Drive
Morgan Drive will be closed between Lantern Road and Emmanual Court for work on stormwater structures.
106th Street
Crews will be landscaping the center of the roundabout at 106th Street and Geist Road throughout the week, weather permitting. Temporary lane restrictions may be in place as work is completed.
In an effort to locate utilities at the intersection of 106th Street and Allisonville Road, the westbound lane of 106th Street (just east of Allisonville Road) will be closed until all utilities are located. Westbound traffic on 106th Street will be forced to turn north.
Interstate 69
As part of a $92 million design-build contract, Milestone has added a third lane in each direction to the median, repaired and resurfaced existing pavement, and rehabilitated bridges and drainage structures on 15 miles of I-69 in Hamilton and Madison counties. Construction of an additional auxiliary lane between the 116th Street entrance ramp to I-69 South and the I-69 South Exit 204 ramp to 106th Street will continue through next spring.
I-69 South will be temporarily reduced to two lanes to allow space for the State Road 37 and 116th Street entrance ramps to safely merge while construction continues on the southbound auxiliary lane between the 116th Street and 106th Street ramps.
Questions about this project should be directed to INDOT via email or at 1-855-463-6848.