Carmel road construction updates

U.S. 31 traffic alert from INDOT

The Indiana Department of Transportation will begin bridge maintenance on a number of bridge decks on U.S. 31 in Hamilton County. The work will be on both directions of U.S. 31 from 181st Street to Range Line Road and is scheduled to be complete mid-October. During construction, there will be intermittent lane closures and ramp restrictions. There will always be one lane open in each direction on U.S. 31 throughout construction.

The only full closures scheduled in this project are the Keystone/U.S. 31 ramps. Details on those closures will come at a later date. For the latest updates about closures and lane restrictions, follow @INDOTEast on Twitter and INDOT East Central on Facebook.

Range Line Road and Walnut Street
(formerly 6th Street South)

Project start date: July 12, 2021
Estimated time frame: 60 days

111th Street and Westfield Boulevard
Project start date: July 12, 2021
Estimated time frame: 35 days

Veterans Way

The ongoing Duke Transmission project and preliminary water utility work has begun on Veterans Way between the Cat Theatre, just north of Elm Street and 1st Street SW. There will be partial closures of the roadway but access to all addresses on this block will be maintained.

Street Department Maintenance

Annual maintenance of Carmel streets will be ongoing through the summer; partial closures for milling operations followed by resurfacing throughout the city. Click here for a full list of paving projects.