The City of Noblesville is sharing updates, details, and interesting aspects about the Reimagine Pleasant Street project to keep you updated on its progress. Stay informed by following along on Twitter and Facebook.
Upcoming road closures & detour
Road closures related to Reimagine Pleasant Street have begun and will continue through April and May, leading up to the closure of 8th Street and Pleasant Street after Memorial Day. The official detour route may be used during the entirety of the Eighth Street and Pleasant Street closure. The detour route is designed to remain consistent throughout all road closures during the 2023 construction season.
Temporary signals will be added on Hannibal Street at the intersections of 8th and 10th streets. Traffic is anticipated to settle into regular patterns over a period of about two weeks, during which the project team will monitor the detour route. Adjustments may be made during or after the two-week period if required.
Bridge construction
Drilling operations for the bridge foundation shafts continue on the east side of the White River. Pile driving operations will begin once the drilled shafts are complete. Residents in the area may notice additional noise while pile driving occurs. This work will not happen before 7 a.m. or after 6 p.m.
Tree plantings
More than 1,500 trees will be planted along the entire Pleasant Street corridor. In fact, more than 20 native Indiana tree and shrub species are being planted as part of the project.
Recent public information meeting
Thank you to everyone who came to the public information meeting last month. If you weren’t able to attend, you can view the presentation and materials at this link.