A pre-construction phase at SR 37 and 141st Street is currently in place. During this phase, 141st Street will be transitioned to a Right-In-Right-Out (RIRO) traffic configuration.

This is not the permanent configuration. This will allow for traffic to flow more freely along SR 37 until the next phases of construction can be activated. This will eliminate all backups along SR 37 that have caused dangerous stops to the free flow traffic and backups on the 146th Street interchange. Again, this is not the permanent configuration for 141st Street.

The full timeline for the 141st Street interchange will be provided after project bids are accepted in the summer of 2023. View detour routes here.

Cumberland Road

Beginning on Monday, March 13, there will be lane closures on Cumberland Road, just south of 126th Street for sanitary and water line work. The northbound right turn lane and the southbound passing blister will be closed for approximately two weeks.

From Monday, March 13, through Friday, March 24, there will be daily lane restrictions between 9 a.m. and 3:30 p.m. on Cumberland Road between 106th Street and 116th Street for tree clearing as part of the Cumberland Road Reconstruction project. There may be  times when a short-term full road closure will be needed. Finding an alternate route is recommended during this time. For additional project information, view the Capital Project Dashboard here.

131st Street

Comcast is currently doing utility work on 131st Street from Howe Road to Promise Road then north on Promise Road to 141st Street. Lane restrictions will be in place between 9 a.m. and 3 p.m.

106th Street & Hoosier Road

Utility relocation is currently taking place at 106th Street and Hoosier Road as part of the roundabout project. For additional project information, view the Capital Project Dashboard here.

Geist Greenway

Pile driving activities are currently taking place near Thorpe Creek as part of the Geist Greenway Project through Monday, March 20. When material is brought in for fill sections, there will be an increase in construction traffic on Valley Crossing Drive. Traffic will be briefly stopped as trucks are entering and exiting the road. For general project information, please visit playfishers.com/299/Geist-Greenway.

Fall Creek Road

Citizens Energy Group is mobilizing the lift station on Fall Creek Road near Geist Woods Way, resulting in the closure of Fall Creek Trail in the area until the project is complete in August.

Resurfacing Projects

Beginning on Monday, March 13, ADA ramp and curb reconstruction will take place in Winding Creek as part of the 2023 Resurfacing Project.

Homeowners will be notified via door hangers prior to any curb restoration near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Prior to road resurfacing, residents will be notified via street signage for street parking restrictions. For additional project information, view the Capital Project Dashboard here.