113th Street
Lane restrictions will begin on 113th Street between Olio Road and Florida Road on Monday, March 19, to allow for tree clearing prior to the construction of a trail and new roundabout. Restrictions will occur between 9 a.m. and 3 p.m., and flaggers will be in place to direct traffic.
106th Street
106th Street is closed to through traffic from Eller Road to Allisonville Road for the 106th Street Infrastructure Project. Closures for through traffic will also take place on Eller Road from Allisonville Road to Hague Road. For more info on this project, view the Fact Sheet.
Hoosier Road
Beginning on or after March 19, Hoosier Road south of 116th Street will be closed to all traffic through the cemetery for sanitary sewer repairs. A detour will be in place on Cumberland Road while work is completed.
131st Street
Periodic lane restrictions will occur at the intersection of 131st Street and Cumberland Road as utility relocation work is completed.
Expect lane restrictions, weather permitting, along 131st Street between Allisonville Road and Lantern Road to allow for tree clearing prior to the construction of the Conner Trail from Conner Prairie to the Municipal Complex. Lane restrictions will also take place on Lantern Road between 131st Street and Municipal Drive.
136th Street
Lane restrictions will be in place, weather permitting, along 136th Street between Southeastern Parkway and Prairie Baptist Road to allow for tree clearing prior to the construction of a new roundabout.
Meadows Drive
Meadows Drive is closed between Frances Drive and Morgan Drive, weather permitting, for the installation of sanitary sewer.
Eller Road
Eller Road is closed to through traffic south of 106th Street. Also, the intersection of 106th Street and Eller Road will be closed for two to three weeks for the 106th Street Infrastructure Project.
126th Street
Expect possible lane restrictions on 126th Street from Allisonville Road to the railroad tracks while aerial utility work is completed.
Allisonville Road Resurfacing & Intersection Improvements Project
Lane restrictions will be in place, as weather permits, along Allisonville Road from 126th Street to 131st Street for tree clearing ahead of the start of the roadway expansion project. Restrictions will be in place between 9 a.m. and 3 p.m. and flaggers will be on site directing traffic, as necessary. For more info on this project, view the Fact Sheet.
Morgan Drive
Morgan Drive is restricted to one lane between Lantern Road and Emmanual Court for work on stormwater structures.
Interstate 69
As part of a $92 million design-build contract, Milestone has added a third lane in each direction to the median, repaired and resurfaced existing pavement, and rehabilitated bridges and drainage structures on 15 miles of I-69 in Hamilton and Madison counties. Construction of an additional auxiliary lane between the 116th Street entrance ramp to I-69 South and the I-69 South Exit 204 ramp to 106th Street will continue through next spring.
I-69 South will be temporarily reduced to two lanes to allow space for the State Road 37 and 116th Street entrance ramps to safely merge while construction continues on the southbound auxiliary lane between the 116th Street and 106th Street ramps.
Questions about this project should be directed to INDOT via email or at 1-855-463-6848.
State Road 37
The State Road 37 improvement project is a $124 million joint project between Fishers, Hamilton County, Noblesville, and INDOT. Questions or concerns may be directed via email to Drive Fishers.